A-REKO PHARMACAL PVT LTD Lahore JANUARY- 2006 to Mar 2013
INSTALLATION PHASE- during Project Engineer (2006-2008)
HVAC INSTALLATION
1st Task During project Engineer was to installed HVAC equipment’s.
210 RT Absorption Job.
Preparation of Project BOQ
Project Drawing, working Drawing, detail drawings.
M.S Pipe work
G.I Duct work
Installation& commissioning of Absorption Chiller.
Installation & commissioning of Compression Chiller
Installation & commissioning of Air Handling Unit.
Installation & commissioning of Cooling Tower.
Installation & commissioning of Desiccant Type Dehumidifier.
Installation & commissioning of Centrifugal water circulating pump.
Installation & commissioning of D.X Refrigerant Dehumidifier.
ELECTRICAL INSTALLATION
2nd Task During project Engineer was to provide the new Electrification system for whole HVAC system and production Machinery & lighting system.
• Electrical Distribution system (power & Light).
• Load Calculation of Electrical System.
• Installation of Main Electrical Panel, Power Distribution Boards& Light Distribution Boards.
• Power Electrical wiring & Light electrical wiring.
• Installation & commissioning of Gas Generator Diesel Generator of different Ratings.
• Good knowledge of LTV line & Power factors.
PHARMACEUTICAL MACHINES INSTALLATION
3rd Task during project Engineer was to Installed the Pharmaceutical Machinery of Production Plant.
• Experience of Tablet Section Machines, Liquid Syrup Machines,
• Dry Syrup Machines, Inject able Section Ointment Section.
• Installation of Quality Control equipment.
• Humidity, Temperature, Air Pressure according to the Manufacturing Requirement.
• Experience of Electrical Maintenance & Mechanical Maintenance of Pharmaceutical Machines.
OPERARTIONAL PHASE Since (2009-present)
I was working as a Assistant Manager Maintenance (Operation).performing the job in operation & look after the whol
Project Engineer